05.05.2008 UCTE-IPS/UPS Feasibility Study: key conclusions endorsed by study partners
The study analysing the feasibility of a possible synchronous coupling of the power systems of IPS/UPS with UCTE has been completed after a 3-year investigation phase. Based on the study results UCTE has been worked out and endorsed together with its Eastern project partners the key conclusions of the study...
(read or download Press Release, Key Conclusions)
23.04.2008 UCTE-IPS/UPS Feasibility Study investigation phase completed
The 3-year investigation phase of the study analysing the feasibility of a possible synchronous coupling of the power systems of IPS/UPS with UCTE has been completed. Based on the study results UCTE worked out together with its Eastern project partners key conclusions...
(read or download news)
22.12.2006 UCTE-IPS/UPS Feasibility Study: Important Milestones reached in December 2006
The study investigating the feasibility of a possible synchronous interconnection of the power systems of IPS/UPS with UCTE is unique with respect to its scope and ambitions. Two major milestones have been reached in December:..
(read or download news, summary)
16.11.2005 UCTE-IPS/UPS Study: Leading associations and stakeholders met in Brussels.
High level representatives of the EU Commission, ministries of the main involved countries and backing organizations exchanged views 6 months after launching the study. The stakeholders met on 16 November in Brussels...
(see attachment)
17.10.2005 Common working activities started in Hanover.
In the beginning of October more than 70 international experts of the electricity transmission industry met in Hanover, Germany, to discuss the technical feasibility of enlarging the continental European interconnected power system to the East...
(see attachment)
20.04.2005 UCTE-IPS/UPS electricity transmission system study has started.
With the active support of the European Commission, the largest system study in the history of UCTE was kicked-off on 20 April 2005 in Brussels after several years of preparation.
This project deals with the investigation of the feasibility of a future synchronous interconnection of the electricity transmission systems of UCTE and IPS/UPS in order to support further developments of electricity markets...
(see attachment)
|