UCTEIPSUPS UCTEIPSUPS Home  |  Contact  |  Masthead  |  Newsletter   
  Home

UCTEIPSUPS

Feasibility Study: Synchronous Interconnection of the
Power Systems of IPS/UPS with UCTE

UCTEIPSUPS

Project Profile

From the beginning...

In 2002 UCTE1 received a request from RAO UES Russia acting on behalf of EPC CIS2 and the Baltic States for a synchronous interconnection of the IPS/UPS3 power systems with UCTE. After the completion of a pre-feasibility study in 2003 dealing with steady state system analysis, UCTE decided to launch a broad feasibility study in order to answer the three main questions:

  • Is a synchronous interconnection of IPS/UPS and UCTE possible?
  • What measures have to be taken on both sides?
  • What are the associated costs?

The results of the three years project will be used as a basis for further decisions on system extension on both sides.

The challenge: one “heart beat” from Lisbon to Vladivostok

The feasibility study is another milestone in the history of UCTE: the interconnection would finally lead to synchronously interconnected power systems with a total installed capacity of 800 GW spanning 13 time zones and serving about 800 million customers. Presently, there is no existing example in the world which operates in synchronous mode in this extension.

The study will be performed as a joint project under the responsibility of UCTE. More than 100 experts from both sides are involved in the project. This huge amount of personnel resources is an attribute not only to the size of the system to be investigated, but also to the broad aspects of the tasks to be fulfilled: each of the two synchronous systems has been developed independently in technical, organizational and legal terms in the past. The overall project budget amounts to approximately 10 Million €.

Organisation and time frame

The UCTE-Consortium responsible for the project consists of 11 TSOs from 9 countries, namely: E.ON Netz GmbH (Germany), ELIA System Operator S.A. (Belgium), MAVIR Hungarian Power System Operator Company (Hungary), Natsionalna Elektricheska Kompanbia EAD (Bulgaria), PSE-Operator S.A. (Poland), Red Electrica de Espana S.A. (Spain), Reseau de Transport d'Electricite (France), RWE Transportnetz Strom GmbH (Germany), Slovenska elektrizacna prenosova sustava, a.s. (Slovak Republic), National Power Grid Company “Transelectrica” (Romania) and Vattenfall Europe Transmission GmbH (Germany).

On IPS/UPS-side a group of 7 companies have established a joint agreement for the project: Belenergo (Belarus), Eesti Energia (Estonia), Latvenergo (Latvia), Lietuvos Energia AB (Lithuania), Ukrenergo (Ukraine), Moldelectrica (Moldova) and System Operator - Central Dispatch Organisation of Unified Energy System of Russia (RAO UES) which has the leading role for the Eastern partners.


General project organization:
a joint structure from the working to the Board level

On the working level five working groups deal with the subtasks steady state analysis, system dynamics, power system control, operational and organizational issues and legal aspects. All internal and external activities are coordinated by the project management. Further project entities are:

  • a Project Representative Board, which accompanies the project on the political level with representatives from the European Parliament, European Commission, UCTE, Baltic States and CIS countries
  • a Project Management Board, which is responsible for steering the project and deciding of further steps as well as of approving of reports. This joint board consists of representatives from UCTE and IPS/UPS.

The total project duration of three years – until April 2008 – is globally divided into several main phases such as data collection and modeling, system simulation and verifying and summarizing of results.


The working schedule:
an ambitious time frame for the challenging investigations

In early 2004 a Cooperation Agreement between the UCTE-Consortium and the IPS/UPS companies has been prepared. The agreement defines - on a legal basis - the overall framework of the cooperation between both parties. The Cooperation Agreement was signed during the project kick-off on 19-20 April 2005 in Brussels.

1 UCTE: The "Union for the Co-ordination of Transmission of Electricity" (UCTE) is the association of transmission system operators in continental Europe.
2 EPC CIS: Electric Power Council of Commonwealth of Independent States
3 IPS/UPS: Comprises the Power Systems of the Baltic States (Latvia, Lithuania, and Estonia), Armenia, Azerbaijan, Belarus, Georgia, Moldova, Kazakhstan, Kyrgyzstan, Russia, Tajikistan, Ukraine and Uzbekistan.

 
top
   
  News
 
 05.05.2008

UCTE-IPS/UPS Feasibility Study: key conclusions endorsed by study partners

 23.04.2008

UCTE-IPS/UPS Feasibility Study investigation phase completed

 22.12.2006

UCTE-IPS/UPS Feasibility Study: Important Milestones reached in December 2006

 16.11.2005

Leading associations and stakeholders met in Brussels.